Building work involves more than obtaining planning permission and appointing a contractor. Before construction can proceed, developers and property owners may also need to demonstrate that their proposals meet the relevant building regulations.
One of the most common concerns is how long the approval process will take. A delay in obtaining building control approval can affect contractor availability, project budgets and the overall construction programme. For developers working to tight deadlines, understanding the likely timescale is essential.
In England, the time required depends on the type of building control application, the complexity of the proposed work and whether the submitted information is complete. A full plans application generally receives a decision within five weeks, although this can be extended to two months with the applicant’s written agreement.
However, receiving a decision on the plans is not the same as completing the building control process. Inspections must take place during construction, and a completion certificate may only be issued once the work has been completed and the relevant compliance requirements have been satisfied.
This guide explains the different approval routes, their timescales and the factors that can affect how quickly a project progresses.
How Long Does Building Regulations Approval Take?
The timescale depends largely on the application route selected.
For a standard full plans application submitted to a local authority in England, the authority must notify the applicant of its decision within five weeks of receiving the application. This period can be extended by written agreement, up to two months.
A building notice follows a different process. It does not involve the same formal assessment and approval of detailed plans before work begins. For eligible projects, work can generally start after the required notice period, but this should not be mistaken for formal approval of the design.
The main routes are:
- Full plans application: A decision is generally required within five weeks, or within two months where an extension is agreed in writing.
- Building notice: Eligible work can generally begin after the required notice period, usually at least two clear working days after submission.
- Higher-risk building applications: These follow a separate Building Safety Regulator process with different statutory determination periods.
- Regularisation: Retrospective applications for unauthorised work do not have one standard determination period and may take longer, particularly where inspections or corrective work are required.
The initial decision is only one part of the process. The overall time before a project receives its completion certificate will depend on construction progress, inspection arrangements and the quality of the completed work.
What Affects the Time Taken to Get Building Regulations Approval?
Even where a statutory decision period applies, the actual time needed to prepare and secure approval can vary considerably.
1. The Complexity of the Proposed Work
A straightforward domestic alteration is unlikely to require the same level of technical scrutiny as a new commercial building or a large residential development.
More complex projects may require detailed structural calculations, fire safety information, drainage proposals, energy performance details and specialist reports.
The building control body must assess the submitted information against the applicable technical requirements. Where the project involves several technical disciplines, resolving queries can add time to the process.
2. The Quality and Completeness of the Application
Incomplete drawings, missing calculations or unclear construction specifications can slow down an application.
For example, a proposal involving the removal of a load-bearing wall may require structural calculations and details of the proposed support. If these are missing, the building control body may need further information before it can properly assess the work.
Preparing a coordinated submission before applying can reduce unnecessary exchanges and help the assessment proceed more efficiently.
3. The Need for Specialist Consultation
Some projects require input from other bodies or technical specialists.
Fire safety considerations, drainage arrangements, access requirements and structural design may all require additional information or consultation, depending on the nature of the work.
Where a project involves a building to which the Regulatory Reform (Fire Safety) Order 2005 applies, a building notice may not be an available route. A full plans application may be required.
4. Changes to the Design
A developer may need to revise drawings or specifications after the application has been submitted.
Changes can arise because of technical feedback, new site information, structural considerations or the need to demonstrate compliance with a particular requirement.
Minor clarifications may be dealt with relatively quickly, but substantial revisions can require further assessment and affect the project timetable.
5. The Building Control Route Selected
Choosing between full plans, a building notice or a private registered building control approver can affect how the project is assessed and managed.
The appropriate route depends on the type of building work, the building’s risk classification and whether the relevant statutory requirements allow the chosen procedure.
The quickest route is not necessarily the most suitable. Developers should consider the level of design certainty, technical complexity and need for formal approval before deciding.
How Long Does a Full Plans Application Take?
A full plans application is generally the more thorough route because detailed drawings and supporting information are examined before the work proceeds.
Under the Building Regulations 2010, as amended, the local authority must notify the applicant of its decision within five weeks of receiving a valid application. A longer period of up to two months may be agreed in writing.
The authority may grant the application, grant it subject to specified requirements or reject it where the statutory grounds for rejection apply.
This route is often appropriate for:
- New residential developments.
- Extensions involving complex structural work.
- Commercial buildings.
- Projects involving significant fire safety considerations.
- Alterations where detailed technical approval is important before construction begins.
Although the statutory decision period provides a useful planning benchmark, it does not mean that every application will be approved within that time. Missing information, technical queries and design changes can affect the wider programme.
How Quickly Can Work Start Under a Building Notice?
A building notice is generally intended for smaller and less complex domestic projects where detailed plans do not need to be formally approved before work begins.
For eligible work, construction can generally start after the local authority has received the required notice and the applicable waiting period has passed. This is usually at least two clear working days.
However, a building notice does not provide the same advance assessment of detailed plans as a full plans application. The building control body will inspect the work at relevant stages and may request further information to establish compliance.
If the work does not meet the Building Regulations, the owner may have to make changes at their own expense.
A building notice is therefore not automatically the best option simply because it allows work to start sooner. It is important to establish whether the project is eligible and whether the design is sufficiently developed to manage the risks.
How Long Does It Take to Get a Building Regulations Completion Certificate?
Receiving approval for the plans does not mean the building control process is finished.
During construction, the relevant building control body must be notified at specified stages so that inspections can take place. These may include foundations, drainage, structural elements, insulation and other work that needs to be checked before it is covered up.
Once the work is complete, the building control body will consider whether the relevant requirements have been met.
For qualifying local authority full plans applications, GOV.UK states that a completion certificate will usually be issued within eight weeks of completion, provided the work complies with the Building Regulations.
The certificate is an important record of the building control process. It may be requested during a property sale, refinancing or other property transaction.
Outstanding defects, missing certificates or incomplete inspection records can delay its issue.
How Long Does Higher-Risk Building Approval Take?
Higher-risk buildings are subject to a separate building control regime under the Building Safety Act 2022.
Applications for building control approval involving higher-risk buildings are generally dealt with by the Building Safety Regulator rather than the ordinary local authority building control route.
The statutory determination periods differ according to the type of application and work involved. For example, applications for new higher-risk buildings and applications for work to existing higher-risk buildings have different decision periods.
These projects also involve additional regulatory requirements, documentation and dutyholder responsibilities. Developers should therefore allow for a more detailed approval process and confirm the applicable timetable with the Building Safety Regulator before setting construction dates.
What Happens If Building Regulations Approval Is Delayed?
A delay can affect more than the date construction begins. It may have financial and contractual consequences for the wider development.
For example, a contractor may need to be rescheduled, materials may have to be reordered and financing arrangements may be affected. Where a project is linked to a property sale or commercial lease, delays may also affect completion commitments.
If an application is taking longer than expected, the applicant should:
- Confirm that the application has been received and is complete.
- Check whether the building control body has requested additional information.
- Respond promptly to technical queries.
- Ask whether revised drawings or calculations are required.
- Review the construction programme and identify activities that depend on approval.
- Keep a written record of communications and agreed timescales.
For full plans applications, applicants should also distinguish between a statutory decision period and an agreed extension. The authority’s failure to notify the applicant within the applicable period does not automatically mean that approval has been granted.
Can You Start Building Work Before Approval Is Granted?
The answer depends on the application route and the nature of the work.
Under a building notice, eligible work can generally begin after the required notice period. Under a full plans application, work may also be able to start before the authority has issued its decision, but doing so can expose the owner to risk if the plans are later found not to comply.
Starting work without resolving important technical issues may result in alterations, additional costs or enforcement action.
For projects where structural integrity, fire safety or other significant technical requirements are involved, obtaining a decision on the submitted plans before starting is generally the more prudent approach.
Planning permission and building regulations approval should also be treated separately. Planning permission does not establish that a building complies with the Building Regulations, and building control approval does not remove the need for planning permission where it is required.
How Can You Avoid Delays in the Building Regulations Process?
A well-planned submission can make a significant difference to the time needed to progress a project.
Before applying, consider the following:
Prepare complete technical drawings: Ensure the plans clearly show the proposed work and include relevant construction details.
Obtain structural calculations where necessary: Structural alterations should be supported by appropriate engineering information.
Check fire safety requirements: Establish whether the project involves additional fire safety information or consultation.
Select the correct application route: Confirm whether full plans, a building notice or another approval process is appropriate for the proposed work.
Coordinate the project team: Architects, structural engineers, contractors and other specialists should work from consistent information.
Allow time for inspections: Include building control inspections and the completion certificate process in the construction programme rather than treating them as last-minute tasks.
These measures can help reduce avoidable delays and give property owners and developers a more realistic understanding of when work can begin and when the project can be signed off.
How Charrette Law Can Help with Building Regulations Matters
Building regulations requirements can affect the design, construction and future use of a property. Delays or misunderstandings about the approval process can create complications for developers, property owners and contractors.
Whether you are planning an extension, preparing a new development or dealing with questions about building control compliance, understanding the relevant requirements and how they interact with planning permission is important.
Charrette Law can be contacted to discuss your planning and property-related requirements and establish whether its services are suitable for your circumstances. Understanding the legal and regulatory considerations early can help you assess potential issues before they affect your development programme.
Frequently Asked Questions
Is building regulations approval always required before work starts?
Not every type of building work requires a formal application, as certain work may be exempt. Where approval is required, the correct application or notification procedure should be followed. The applicable route depends on the nature of the work and the building.
How long does a full plans building regulations application take?
In England, the local authority must generally notify the applicant of its decision within five weeks of receiving the application. This can be extended to two months if the applicant agrees in writing.
Can I start work while waiting for building regulations approval?
In some circumstances, work can begin before a full plans decision is issued, but this is at the owner’s risk. Eligible building notice work can generally start after the required notice period. It is important to understand the consequences before proceeding.
Does building notice mean I have building regulations approval?
No. A building notice does not provide the same formal approval of detailed plans as a full plans application. The work must still comply with the Building Regulations and will be subject to inspection.
How long does it take to receive a completion certificate?
For qualifying local authority full plans applications, a completion certificate is usually issued within eight weeks of the work being completed, provided the relevant requirements have been satisfied. Outstanding issues can delay the certificate.
Can building regulations approval be refused?
Yes. A full plans application may be rejected where the statutory grounds for rejection apply, including where the plans do not demonstrate compliance with the Building Regulations. The applicant may need to revise the plans or consider the available review or appeal procedures.
Does planning permission take the same amount of time as building regulations approval?
No. Planning permission and building regulations approval are separate processes with different purposes and decision-making procedures. A project may need both, and their respective timescales should be included in the development programme.
Can I obtain building regulations approval after the work has been completed?
In some circumstances, a property owner can apply for a regularisation certificate from the local authority for unauthorised building work carried out after 11 November 1985. The authority may require inspections and corrective work before issuing a certificate. Regularisation is not guaranteed and is different from obtaining approval before construction.