Can You Get Building Regulations Approval After Building? A Guide to Retrospective Approval

Building Regulations Approval

Completing building work without obtaining the necessary Building Regulations approval can create problems long after construction has finished. A property owner may discover that an extension was never inspected, a structural alteration was carried out without building control involvement, or previous owners failed to provide the relevant completion certificate.

These issues can become particularly important when selling a property, arranging a remortgage or carrying out further development. Buyers and solicitors may request evidence that the work complied with the applicable Building Regulations, leaving the owner with the task of addressing missing documentation.

Fortunately, it may be possible to obtain retrospective approval through a process known as regularisation. However, this is not an automatic approval of completed work. The local authority must be satisfied that the relevant requirements have been met, and it may require inspections, investigations or remedial work before issuing a certificate.

This guide explains how to obtain Building Regulations approval after construction, the regularisation process, the potential costs and what happens when the completed work does not meet the required standards.

 

Can You Get Building Regulations Approval After Building?

 

Yes. In England, you may be able to obtain retrospective Building Regulations approval through a regularisation application.

Regularisation is a formal process that allows a property owner to apply to the local authority building control body for a certificate covering certain building work carried out without the required building control approval or notification.

Under Regulation 18 of the Building Regulations 2010, this route is available for qualifying unauthorised building work carried out on or after 11 November 1985.

However, there are important limitations:

  • The application must be made to the local authority building control body. You cannot appoint a private registered building control approver to regularise work that has already been completed without the necessary building control process.
  • The work must be assessed against the relevant Building Regulations requirements that applied when it was carried out.
  • The local authority may require parts of the construction to be exposed for inspection.
  • Additional work may be necessary before a regularisation certificate can be issued.

The purpose is to establish whether the completed work satisfies the relevant standards, not simply to provide paperwork for construction that has already taken place.

 

 

What Is a Regularisation Certificate?

 

A regularisation certificate is a document issued by the local authority building control body where it is satisfied that qualifying unauthorised building work complies with the relevant Building Regulations requirements.

It provides evidence that the specified work has been assessed and that the authority is satisfied that the applicable requirements have been met.

For example, a homeowner may have constructed a rear extension several years earlier without submitting a building control application. If the work was subject to Building Regulations, the owner may apply for regularisation so that the authority can investigate compliance.

Where the authority is satisfied that the relevant requirements have been met, it may issue a regularisation certificate.

It is important to understand that a regularisation certificate is evidence of compliance, but it is not conclusive evidence in every legal context. It also covers the work identified in the certificate rather than automatically certifying every part of the property.

 

When Might You Need Retrospective Building Regulations Approval?

 

There are several circumstances in which a property owner may discover that building work was completed without the appropriate approval.

1. When Buying a Property with Missing Building Control Documents

A buyer may discover during conveyancing that an extension, loft conversion or structural alteration has no Building Regulations completion certificate.

This can raise questions about whether the work was properly inspected and whether it meets the required standards.

Where the work was carried out without the necessary approval, the buyer or current owner may need to investigate whether a regularisation application is appropriate.

2. When Previous Owners Carried Out Unauthorised Work

A property owner may inherit a building control problem without having carried out the original construction.

For example, a previous owner may have removed an internal wall, converted a garage or installed a new staircase without obtaining the necessary approval.

The absence of documentation does not automatically establish that the work is defective, but it may make it difficult to demonstrate compliance.

A review of the property’s records and the nature of the work can help establish what action is needed.

3. When an Extension Was Completed Without Inspection

An extension may have been constructed without a building notice or full plans application being submitted.

Even where the work appears structurally sound, important elements such as foundations, drainage, insulation and fire safety may not have been inspected.

A regularisation application can allow the local authority to investigate whether the work meets the applicable standards.

4. When Structural Alterations Were Made Without Approval

Removing load-bearing walls, changing structural supports or altering roof structures can affect the safety and stability of a building.

Where such work was completed without the required building control process, the owner may need to provide structural calculations, arrange further investigations or undertake remedial work.

This is particularly important where the alterations affect the building’s overall structural integrity.

How to Get Building Regulations Approval After Building

Obtaining retrospective approval involves more than submitting a request for a certificate. The local authority needs enough information to establish whether the completed work meets the relevant requirements.

Step 1: Identify the Work That Was Completed

Start by establishing exactly what building work was carried out and when it was completed.

This matters because the relevant Building Regulations are generally those that applied at the time the work was undertaken.

Identify whether the work involved:

  • Constructing an extension or new structure.
  • Converting a loft or garage.
  • Removing or altering structural walls.
  • Changing drainage or plumbing arrangements.
  • Replacing or modifying fire safety provisions.
  • Altering insulation, ventilation or heating systems.

You should also establish whether the work was exempt from Building Regulations or could have been certified through a competent person scheme.

Not every missing completion certificate means that a regularisation application is necessary.

Step 2: Contact the Local Authority Building Control Department

For ordinary qualifying building work that has already been completed without the required building control process, regularisation applications are made through the relevant local authority.

It is sensible to discuss the circumstances with the authority before submitting an application.

Explain what work was undertaken, when it was completed and whether any drawings, calculations or previous correspondence are available.

The authority can explain its application requirements, likely inspection arrangements and applicable fees.

Step 3: Prepare the Regularisation Application

Under Regulation 18 of the Building Regulations 2010, the application must include certain information, including:

  • A statement confirming that the application is for regularisation.
  • A description of the unauthorised building work.
  • A plan of the work, so far as reasonably practicable.
  • Plans showing any additional work that may be needed to achieve compliance, so far as reasonably practicable.

Depending on the project, the authority may also request structural calculations, specifications, photographs, drainage details or other technical evidence.

For complex alterations, an architect, structural engineer or other suitably qualified professional may be needed to prepare the supporting information.

Step 4: Arrange an Inspection of the Completed Work

The local authority will need to assess the work to establish whether it meets the applicable requirements.

An inspection may involve examining visible construction elements and reviewing available technical information.

However, completed work can present a particular difficulty: important components may already be concealed behind plasterboard, flooring, ceilings or external finishes.

For example, the foundations of an extension may be hidden beneath the finished floor, while structural supports may be enclosed within walls or ceilings.

The authority may therefore require reasonable steps to expose parts of the construction so that compliance can be assessed.

This is often referred to as opening up the work.

Step 5: Complete Any Required Remedial Work

If the inspection identifies areas that do not meet the relevant requirements, the authority may specify what additional work is necessary.

Depending on the findings, this could involve:

  • Strengthening structural elements.
  • Improving fire protection.
  • Correcting drainage defects.
  • Installing appropriate insulation.
  • Improving ventilation.
  • Rectifying inadequate damp-proofing.
  • Making alterations to stairs, access or escape arrangements.

The extent of the remedial work will depend on the nature of the original construction and the requirements that applied when it was undertaken.

Where significant defects are identified, the cost of achieving compliance may be considerably higher than the cost of obtaining approval before construction began.

Step 6: Obtain the Regularisation Certificate

Once the local authority has taken reasonable steps to establish that the relevant requirements have been satisfied, it may issue a regularisation certificate.

The certificate identifies the work covered and provides evidence that the authority is satisfied with its compliance.

If the authority cannot establish compliance, it may be unable to issue the certificate.

The owner should retain the certificate and supporting documents as part of the property’s building control records.

 

What Happens If the Building Work Does Not Meet Building Regulations?

 

Submitting a regularisation application does not guarantee that the local authority will approve the work.

If the inspection identifies defects, the authority may require further investigations or remedial construction before it can consider issuing a certificate.

For example, an extension with inadequate foundations may require additional structural investigation and potentially substantial corrective work.

Similarly, a loft conversion without suitable fire protection may need alterations to provide appropriate escape arrangements and compartmentation.

In some cases, the authority may be unable to determine what work is necessary without further investigation. The owner may need to arrange specialist reports or expose concealed construction elements.

It is important to address these issues promptly, particularly where the work creates a safety concern or the authority is considering enforcement action.

 

Can You Get a Regularisation Certificate Without Opening Up the Work?

 

Sometimes, but it depends on whether the local authority can satisfy itself that the work complies without further investigation.

Where construction details are visible or sufficient technical evidence is available, opening up may not be necessary.

However, if important elements are concealed and cannot be properly assessed, the authority may require them to be exposed.

For example, it may be necessary to uncover parts of a foundation, inspect structural supports or investigate drainage installations.

Photographs taken during construction, original drawings, contractor records and structural calculations may help demonstrate how the work was carried out. However, these documents do not automatically remove the need for physical inspection.

The local authority must have sufficient evidence to reach a reasonable conclusion about compliance.

 

How Much Does Retrospective Building Regulations Approval Cost?

 

The cost of a regularisation application varies depending on the local authority, the type of work and the level of investigation required.

Potential expenses include:

  • The local authority’s regularisation application fee.
  • Architectural drawings or revised plans.
  • Structural engineering assessments.
  • Specialist inspections and testing.
  • Opening up concealed construction.
  • Repairs or remedial building work.
  • Additional professional fees.

For example, regularising a straightforward alteration may involve relatively limited investigation, while a major extension or structural conversion could require detailed technical assessments and extensive remedial work.

It is advisable to request a fee estimate from the local authority and obtain professional advice on any likely investigation or construction costs before proceeding.

Can You Sell a Property Without a Building Regulations Completion Certificate?

 

It may be possible to sell a property without a Building Regulations completion certificate, but missing documentation can complicate the transaction.

A buyer’s solicitor may ask for evidence that alterations and extensions complied with the relevant requirements.

If the documentation is unavailable, the buyer may request further information, seek a price reduction or ask the seller to resolve the issue before completion.

Depending on the circumstances, the parties may consider a regularisation application or discuss other ways of addressing the missing documentation.

An indemnity insurance policy may sometimes be considered in a conveyancing transaction, but it does not establish that the building work complies with Building Regulations. It also does not correct defects or provide retrospective approval.

The appropriate approach depends on the nature of the work, the available evidence and the buyer’s requirements.

 

Is There a Time Limit for Getting Retrospective Building Regulations Approval?

 

Under Regulation 18 of the Building Regulations 2010, the regularisation procedure applies to unauthorised building work carried out on or after 11 November 1985.

This is an eligibility threshold for the regularisation process, not a guarantee that older work can be certified or that the authority will overlook non-compliance.

The relevant requirements are generally assessed against the Building Regulations that applied when the work was carried out.

It is also important to distinguish the availability of regularisation from the local authority’s enforcement powers. A regularisation application does not automatically prevent enforcement action or remove any existing legal issue.

Where work is significantly older or falls outside the regularisation procedure, the owner should discuss the available options with the local authority and obtain appropriate advice.

 

What Is the Difference Between Regularisation and Building Regulations Approval Before Construction?

 

Regularisation and ordinary building control approval both relate to compliance with Building Regulations, but they apply at different stages.

Regularisation Approval Before Construction
Used for qualifying work already carried out without the required approval or notification. Used before or during the authorised building control process for proposed work.
Application is made to the local authority building control body. Can generally be handled by local authority building control or a registered building control approver, subject to the applicable rules.
May require opening up completed construction. Allows proposed details to be assessed before they are concealed or completed.
May require remedial work to achieve compliance. Helps identify technical issues before or during construction.
Can result in a regularisation certificate. Can result in the relevant completion certificate once the work has been completed and compliance established.

The main advantage of obtaining approval through the correct process before construction is that technical issues can be identified earlier, when they are generally easier and less expensive to resolve.

 

How to Avoid Building Regulations Problems in Future Projects

 

Retrospective approval can be useful, but it should not be treated as a substitute for proper building control arrangements.

Before starting future building work, consider the following:

Check whether approval is required: Establish whether the proposed work falls within Building Regulations or qualifies for an exemption or competent person scheme.

Choose the right building control route: Confirm whether a full plans application, building notice or another approval process is appropriate.

Use qualified professionals: Obtain suitable architectural drawings, structural calculations and technical specifications where required.

Arrange inspections at the correct stages: Ensure that building control can inspect important construction elements before they are covered up.

Keep complete records: Retain approved plans, inspection reports, certificates and relevant correspondence.

Check planning permission separately: Building Regulations approval does not replace planning permission, and both may be necessary for the same project.

Taking these steps can help protect the property owner from avoidable costs, compliance issues and difficulties during future property transactions.

 

How Charrette Law Can Help with Building Regulations and Property Matters

 

Discovering that completed building work lacks the required approval can create uncertainty, particularly when the issue affects a property sale, further development or compliance with planning and building legislation.

Understanding the available regularisation process, the authority’s enforcement powers and the legal implications of missing documentation is important before deciding how to proceed.

Charrette Law can be contacted to discuss your planning and property-related requirements and establish whether its services are suitable for your circumstances. Taking advice at an early stage can help you identify potential legal issues and understand the options available for addressing them.

 

Frequently Asked Questions

 

Can you get Building Regulations approval after building work is completed?

Yes. In England, qualifying unauthorised building work carried out on or after 11 November 1985 may be eligible for retrospective approval through a local authority regularisation application. The authority must be satisfied that the relevant requirements have been met before issuing a certificate.

Can I get retrospective Building Regulations approval from a private building control inspector?

No. For ordinary qualifying work that has already been completed without the required building control process, the regularisation application must be made to the local authority building control body. A private registered building control approver cannot retrospectively take on the work through the ordinary approval process.

What happens if my regularisation application is refused?

If the authority cannot establish that the work complies with the relevant requirements, it may be unable to issue a regularisation certificate. You may need to provide further evidence, open up concealed work or complete remedial construction before the authority can reconsider the position.

Can I get a regularisation certificate without opening up the building work?

Possibly. If the authority has sufficient evidence to assess compliance, it may not need to require opening-up work. However, where important construction details are concealed and cannot otherwise be verified, further investigation may be necessary.

Can I sell my house without Building Regulations approval?

A sale may still proceed without a completion certificate, but missing documentation can raise questions during conveyancing. The buyer may request additional evidence, seek regularisation or consider other options with their solicitor.

Does regularisation approval mean the work is fully legal?

A regularisation certificate provides evidence that the specified work has been assessed and that the authority is satisfied that the relevant Building Regulations requirements have been met. It does not automatically resolve separate planning permission issues, property title matters or other legal requirements.

How long does retrospective Building Regulations approval take?

There is no single fixed timescale for every regularisation application. The process depends on the complexity of the work, the availability of supporting documents, inspection requirements and whether remedial work is needed.

Can I get retrospective approval for building work completed before 1985?

The regularisation procedure under Regulation 18 applies to qualifying unauthorised building work carried out on or after 11 November 1985. Older work may need to be considered through other available routes, depending on the circumstances and the evidence of compliance.

Is a regularisation certificate the same as a completion certificate?